An update on the progress of East Sunset Heights from Mario Castillo, Houston City Council, District H.
The schedule is on track with a few minor alterations in the sequencing as the contractor adjusts to the conditions of the site.
The contractor discovered and removed contaminated soil in the work area. The soil will be disposed at an approved facility. The contractor received approval and installed a liner to surround the underwater stormwater detention. The Underground stormwater detention system was installed. Stormwater connections and underground electrical and splash pad plumbing installation were completed.
November 2026
The contractor will install South concrete trails, the sidewalk along North Main Street and concrete for the workout area, landscape curbs and pavers. Splash pad seat wall and associated splash pad plumbing and light pole foundations and underground electrical will be installed.
December 2026
Irrigation and concrete trails in the North section of park will be installed. Splash pad installation and poured in place fall surfacing. Paver installation will continue.
January 2027
Installation of playground and workout equipment, fall surfacing lighting and signage. Landscaping and construction of art platform.
February 2027
Installation of site furnishings and completion of landscaping.